SCHEDULE
Start Construction Work: February 2023
Finish Construction: Substantial Completion June 2025
Workdays: Monday - Friday (Some Saturday Work)
Work Hours: 7:00 a.m. to 7:00 p.m.
The city is in the process of bidding and selecting a contractor to perform the Utility Pipeline Project work. This work is scheduled to commence in the Spring of 2023 and extend through the Summer.
The city plans to select a contractor to construct the pump station and the well house in the Fall of 2023 with work anticipated to start in March of 2024.
The City of Orem requested contractor Statements of Qualifications for construction of the Heritage Park 10 Million Gallon Water Tank Project. The Project includes the construction of the tank, pump house, pipe lines and well drilling.
The purpose of the prequalification process is to select contractors the city deems to be qualified and capable of completing the Project in conformance with the Contract Documents. The prequalification statement from contractors included qualifications of personnel, relevant project experience, financial information, risk assessment and contractor certifications.
These listed contractors submitted Statements of Qualifications for the various phases of the Project.
Water Tank
Prequalified:
Dry Creek Structures
ProBuild
MGC Contractors
Sundt Construction
Alder Construction
Gerber Construction
Pipelines
Prequalified:
COP Construction
S&L Inc.
Condie Construction
Red Pine Construction
Newman Construction
Pump House
Prequalified:
J. Lyne Roberts & Sons Inc.
Vancon Inc.
W. W. Clyde
COP Construction
Whitaker Construction
Well Drilling
Prequalified:
Hydro Resources
Lang Equipment
Layne Christensen