top of page

SCHEDULE

Start Construction Work: February 2023
Finish Construction: Substantial Completion June 2025
Workdays: Monday - Friday (Some Saturday Work)
Work Hours: 7:00 a.m. to 7:00 p.m.

The city is in the process of bidding and selecting a contractor to perform the Utility Pipeline Project work. This work is scheduled to commence in the Spring of 2023 and extend through the Summer.

 

The city plans to select a contractor to construct the pump station and the well house in the Fall of 2023 with work anticipated to start in March of 2024.

The City of Orem requested contractor Statements of Qualifications for construction of the Heritage Park 10 Million Gallon Water Tank Project. The Project includes the construction of the tank, pump house, pipe lines and well drilling. 

The purpose of the prequalification process is to select contractors the city deems to be qualified and capable of completing the Project in conformance with the Contract Documents. The prequalification statement from contractors included qualifications of personnel, relevant project experience, financial information, risk assessment and contractor certifications.

These listed contractors submitted Statements of Qualifications for the various phases of the Project.

Heritage Tank Schedule April 2024 sh update.jpg

Water Tank

Prequalified:

Dry Creek Structures

ProBuild

MGC Contractors

Sundt Construction

Alder Construction

Gerber Construction

Pipelines

Prequalified:

COP Construction

S&L Inc.

Condie Construction

Red Pine Construction

Newman Construction

Pump House

Prequalified:

J. Lyne Roberts & Sons Inc.

Vancon Inc.

W. W. Clyde

COP Construction

Whitaker Construction

Well Drilling

Prequalified:

Hydro Resources

Lang Equipment

Layne Christensen

bottom of page